Estimates the number, cost and time of makereadies as well as makeready spoilage sheets.
Operation Setup Requirements:
Operation Setup Requirements:
- Description
- Rate: Cost per hour
- Sell $ use: Markup % (recommended) or alternate sell rate
- Calc: 6
- Sub Key: Labor
- Minutes First: Minutes for first makeready
- Minutes Repeat: Minutes for each additional makeready
- Sheets / MR = Default sheets per makeready
- Base makeready sheets (with option to multiple base x Forms)
- Include makeready sheets in paper order option
- Include makeready sheets in press run option (will also include in paper order)
Estimate Specification Input Prompts:
- Makereadies (Computed if Calc 5, manual if no Calc 5)
- Makeready Sheets (Computed if sheets per makeready and/or base MR sheets defined)
- J%
- Remarks
- Memo
Calculation:
Minutes First + (Makereadies - 1) x Minutes Repeat = Standard Minutes
Standard Minutes / 60 x J% = Estimated Hours
Estimated Hours x Rate = Cost $
Cost $ x Markup % = Markup $
Cost $ + Markup $ = Sell $
Note: Calc 5 followed by a Calc 6 will automatically calculate makereadies